Here's the latest photos sent over from France kindly taken by our builder Tony. They were taken a week or so ago and show the first floor bedrooms and bathroom spaces taking shape together with the first fix electrics. All the walls are being formed in the metal studwork that was the subject of one of my first blogs.
The sloping parts of the ceiling have been insulated and plasterboard fixed to these areas. I noticed something in the photographs that appeared to look like a trestle but after a bit more of looking at I worked out that it was a piece of equipment that is used to load a sheet of plasterboard on then it is mechanically raised to the ceiling for fixing. This certainly takes the back breaking work out of the operation. These can be purchased or hired and the link below will take you to a typical site.
http://www.brandontoolhire.co.uk/lifting-hire/prodview.asp?idproduct=142
I am hoping for some more photographs to be sent this week so will do another post soon. If you missed my blog on the studwall you can find it on the listing on the right for Saturday, 27 November 2010
Sunday, 12 February 2012
Saturday, 11 February 2012
Stair Crazy
The builders have asked for the details of the staircase. We have always said that we wanted something unusual, simple and chunky looking that will be hidden completely behind a wall. The French seem experts in producing creaky staircases and given our exacting requirements this would need to be of a bespoke design and hand made. These are the details that we quickly drawn up.
Together with the drawings the builders were also sent a photograph of a similar staircase that was found on the Internet. If ours turns out like this one we shall be really pleased.
The baluster at the landing level was something else that was a thought about hard and long.First of all we were thinking of glass then developed into something a bit more simple in the form of stainless steel posts and wire. It moved onto wrought iron and is always the case back to our original idea of glass.
For more details on stairs in oak and glass that can be purchased in kit form here are a few links.
http://www.tradestairs.com/acatalog/Vision_Oak_Grooved_Handrails.html
http://www.stairplan.com/townsend-oak-staircase.html
One last thing is that we had a bit of surprise with the discarded floor joists in that they are of oak and have enough to make the treads and risers. Cutting the timbers down to the right dimensions and building up the staircase is going to be a really nice job for the joiners right now particularly as the temperature in France is around about -9 degrees during the day. The inside of the house is bitterly cold especially when the wind gets up and we think on more than one occasion Tony and Steve had to head back home early to get warm.
Together with the drawings the builders were also sent a photograph of a similar staircase that was found on the Internet. If ours turns out like this one we shall be really pleased.
The baluster at the landing level was something else that was a thought about hard and long.First of all we were thinking of glass then developed into something a bit more simple in the form of stainless steel posts and wire. It moved onto wrought iron and is always the case back to our original idea of glass.
For more details on stairs in oak and glass that can be purchased in kit form here are a few links.
http://www.tradestairs.com/acatalog/Vision_Oak_Grooved_Handrails.html
http://www.stairplan.com/townsend-oak-staircase.html
One last thing is that we had a bit of surprise with the discarded floor joists in that they are of oak and have enough to make the treads and risers. Cutting the timbers down to the right dimensions and building up the staircase is going to be a really nice job for the joiners right now particularly as the temperature in France is around about -9 degrees during the day. The inside of the house is bitterly cold especially when the wind gets up and we think on more than one occasion Tony and Steve had to head back home early to get warm.
Saturday, 4 February 2012
Build update
The internal block support wall running up alongside stairway opening is now complete. The new first floor joists all in oak has been installed and trimmed back over the stairwell.
As the floor joists are to be exposed I suggested to the builder that we lay the plasterboard on top of the floor joists before laying the floor board. This would save time later plaster boarding from underneath. This has worked out brilliantly well and all that needs to be done is to carry out plaster skim work and we are done. I had thoughts about the plasterboard crushing under the weight of furniture loading but decided that the floor board would distribute the load sufficiently not be an issue.
We have issued an electrical layout to the builders giving switching positions/arrangements as well as power outlet positions and tv outlets. So we had to carefully think out were we wanted beds and furniture to be put. There has been a change in programme and with the freezing weather setting in any stonework operations is out of question.The builders efforts over the coming are now concentrating on the first floor works,first fixes, insulating and boarding the ceiling.
As the floor joists are to be exposed I suggested to the builder that we lay the plasterboard on top of the floor joists before laying the floor board. This would save time later plaster boarding from underneath. This has worked out brilliantly well and all that needs to be done is to carry out plaster skim work and we are done. I had thoughts about the plasterboard crushing under the weight of furniture loading but decided that the floor board would distribute the load sufficiently not be an issue.
We have issued an electrical layout to the builders giving switching positions/arrangements as well as power outlet positions and tv outlets. So we had to carefully think out were we wanted beds and furniture to be put. There has been a change in programme and with the freezing weather setting in any stonework operations is out of question.The builders efforts over the coming are now concentrating on the first floor works,first fixes, insulating and boarding the ceiling.
Saturday, 7 January 2012
Floors
The last few weeks leading up to Christmas has seen focus switching to the first floor structure. With the chestnut floor boarding removed the builders have been able to inspect the ends of the timber joists that are embedded in the walls.
We were prepared to replace the odd timber or two and also support the joists from the underside with a timber frame to provide additional support and to take some of the deflection out of the floor, re-using some of the old oak roof timbers for the support frame. However, as ever, things have not worked as planned.
The majority of the floor joists are rotten and there is a dip in the floor of about 50mm from one of the building to the other. Weighing up all the options we decided to renew the floor joists in oak. These have worked out to be 200x80 at 450 centres for a span of 5.4m.
So we go into the New Year hoping that the new windows and doors will go in over the next few weeks followed by plastering of ground floor walls. But this is France so who knows!
Sunday, 6 November 2011
Roof complete.
We now have some really interesting dynamics going on in the building which has again changed our thoughts on how we progress with the renovation works. It would be a crime not to keep areas of the stonework. So we have decided to re-point the front and rear walls and to insulate and plasterboard the gable.
Over the next few weeks it is planned to lay the new concrete floor and form the new door and window openings. The new hardwood double glazed doors and windows have been delivered. So it should be all go but this is France so we are not holding our breath!
Sunday, 25 September 2011
Roof nearly complete
Our new roof is nearly complete after what seems an age with house exposed to the elements. The joiners have been taking full advantage of the September sunshine and the timber roof structure is finally in place, fully constructed and trimmed out ready to receive the Velux rooflights.
We were given the news last week that the chimney stack was unstable and needed to be re-built. This came of no great surprise given the age of the property and that the mortar bonding the stonework and brickwork together is clay based (ie mud). The plus side of this is that the stack has been reconstructed re-using the bricks. If you look closely at the photographs you can just see the leadwork that has been built into the brickwork that will be dressed over the tiles.
You will also notice that the there are little columns or pillars to the corners of the stack. These will eventually support a concrete or stone capping slab. This is the french way of doing things although they also have clay chimney pots in much the same way as in the UK. There is also an element of making good of the stonework along the gables and at the wallplate position.
With the rooflights having been picked up by our neighbours and safely stored in their garage and with the tiles having arrived last week together with the felt and battens, fingers crossed we shall have achieved our first construction milestone by the end of the week. At this point we have to thank our friends and neighbours Martin and Angela for taking these photos and keeping us informed on progress and generally "running around" on our behalf ensuring that things dont go wrong - something that often does if you aren't "on site".
We were given the news last week that the chimney stack was unstable and needed to be re-built. This came of no great surprise given the age of the property and that the mortar bonding the stonework and brickwork together is clay based (ie mud). The plus side of this is that the stack has been reconstructed re-using the bricks. If you look closely at the photographs you can just see the leadwork that has been built into the brickwork that will be dressed over the tiles.
You will also notice that the there are little columns or pillars to the corners of the stack. These will eventually support a concrete or stone capping slab. This is the french way of doing things although they also have clay chimney pots in much the same way as in the UK. There is also an element of making good of the stonework along the gables and at the wallplate position.
With the rooflights having been picked up by our neighbours and safely stored in their garage and with the tiles having arrived last week together with the felt and battens, fingers crossed we shall have achieved our first construction milestone by the end of the week. At this point we have to thank our friends and neighbours Martin and Angela for taking these photos and keeping us informed on progress and generally "running around" on our behalf ensuring that things dont go wrong - something that often does if you aren't "on site".
Tuesday, 6 September 2011
Anyone seen my bike?
During the work to remove the existing roof structure of all things a bike was found in the roof space. This was thrown unceremoniously over the wall only to be caught in the ivy growing on the wall. We are thinking of framing this and sending to the builders.
There was a suggestion that we should extend the renovation project to include the bike. Needless to say the bike found its way into the skip.
Now the roof has gone the next job is to level up and strength the existing wall . This is being done by the casting a reinforced concrete ring beam to tie the walls together. The photograph below shows the timber formwork in position ready to receive the reinforcement and concrete. There needs to be a similar beam casting to the front with tie rods connecting them together to form a rigid box. Then the new roof can be put on.Holiday report part 2
During our stay in France, holed up in our little touring caravan waiting for the rain to stop, we had plenty of time to think about how we wanted to renovate the cottage. We decided to discard with the underfloor heating to the ground floor opting instead for a log burning stove kicking out up to 7 KW.
More than enough space heating. We will probably put in a some electric convectors in here and there as background heating for the Winter months when we may not be there.
The biggest decision was to take up the existing clay floor tiles which have been laid directly on the ground and are an original feature of the house. They are 30mm thick so these will be re-bedded onto the new floor construction. They will need a bit of cleaning before they go back down but it will be worth the hard work.
More than enough space heating. We will probably put in a some electric convectors in here and there as background heating for the Winter months when we may not be there.
The biggest decision was to take up the existing clay floor tiles which have been laid directly on the ground and are an original feature of the house. They are 30mm thick so these will be re-bedded onto the new floor construction. They will need a bit of cleaning before they go back down but it will be worth the hard work.
Monday, 8 August 2011
Holiday report part 1
We have just got back from a holiday in France having spent the best part of two weeks in our Caravan pitched up in the back garden of our house. Our friends opposite had cut the grass down to as far as possible and prepared a nice pitch for the van. The builders had opened up the hedge off the lane so we could drive into the back garden, mains water and electric had been laid on and we have 3000 litre fosse to dispose of our toilet waste.
Everything was perfect except we forgot to order the sun. Ten days of continuous rain, seriously stopped any real work on the house and any chance of topping up our tans The previous week scaffold had been erected around the house and the front wall re-built up to approximate floor level. The roof tiles had been removed and broken up for hardcore. Our poor house is now open to the elements with only the skeleton of a roof for protection and the rain continued to fall day after day.
Everything was perfect except we forgot to order the sun. Ten days of continuous rain, seriously stopped any real work on the house and any chance of topping up our tans The previous week scaffold had been erected around the house and the front wall re-built up to approximate floor level. The roof tiles had been removed and broken up for hardcore. Our poor house is now open to the elements with only the skeleton of a roof for protection and the rain continued to fall day after day.
Thursday, 30 June 2011
Stumped
As planned the work has now commenced on renovating our little cottage. First the front wall came down with the stone being reclaimed for re-use at a later date. Soon however, two days of good progress soon came to a halt by a very stubborn Bay tree that occupied the front corner of the house that just refused to be uprooted.
After much scratching of heads involving a couple of architects, the builders, a passing farmer in a tractor with a herd of sheep and many of our neighbours it was decided that we needed a man with a large excavator. So we called upon Ian the guy who installed the fosse to save the day. As is the way in France after a long patient wait of two weeks the devis eventually came through which turned out to be far too expensive. After further head scratching a local municipal works contractor was contacted and the stump finally yielded to a JCB and a very skilled driver.
We are now waiting for the scaffold to be erected so we can start on the roof.
After much scratching of heads involving a couple of architects, the builders, a passing farmer in a tractor with a herd of sheep and many of our neighbours it was decided that we needed a man with a large excavator. So we called upon Ian the guy who installed the fosse to save the day. As is the way in France after a long patient wait of two weeks the devis eventually came through which turned out to be far too expensive. After further head scratching a local municipal works contractor was contacted and the stump finally yielded to a JCB and a very skilled driver.
We are now waiting for the scaffold to be erected so we can start on the roof.
Sunday, 29 May 2011
It's all go!
At long last we have the news we have been waiting for. We now have the permis de construire for the renovation work to our little stone cottage. So everything is set for a start on the work this week.
First we will be digging out for a driveway and also for the courtyard at the back of the house.The topsoil will be stockpiled for future landscaping works and the areas filled with locally sourced crushed stone as hardcore. For the technically minded the stone is graded from dust to 30mm that will compact quite nicely but also lets water percolate through it. The courtyard area will be gravelled to start with but as we start to spend time more time out in France we will probably form some areas of paving here and there.
Also next week I think the front stone wall is being demolished and the offending bay tree dug out. This has been the cause of the wall collapsing and if not removed it will start to give problems with the house foundations We are keeping the stone to use elsewhere, probably to build some ornamental walls in the courtyard area or even used to repair the outhouses.
Wednesday, 18 May 2011
Fosse Septique - Fin
Yesterday our fosse septique was finally completed after a long week toil by our Contractor. It has been passed by the inspectors and for us its the first construction milestone reached.
However, that's not where it quite ends. It is France you see. When asking for the operating and maintenance manuals and guarantee for the pump I could see all of a sudden I needed to learn a third language as I was clearly not being understood. However, being a stubborn sole and really insisting on these things I have been promised that these will be forthcoming but would first need to be collected from the four corners of the earth, before being sent onto us.
I don't think it was so much my powers of persuasion that brought about this sudden change in helpfulness but more of a sudden realisation on the Contractors part that he was still owed quite alot of money. I am now thinking until I get these bits of paper I will with hold just a tiny amount of money from the job.
So from now on there should be no more hedgehogs having to be rescued from open excavations and the build work can now begin .That reminds me, I must check on the planning permission with the Maries office - it has gone really quite!!
However, that's not where it quite ends. It is France you see. When asking for the operating and maintenance manuals and guarantee for the pump I could see all of a sudden I needed to learn a third language as I was clearly not being understood. However, being a stubborn sole and really insisting on these things I have been promised that these will be forthcoming but would first need to be collected from the four corners of the earth, before being sent onto us.
I don't think it was so much my powers of persuasion that brought about this sudden change in helpfulness but more of a sudden realisation on the Contractors part that he was still owed quite alot of money. I am now thinking until I get these bits of paper I will with hold just a tiny amount of money from the job.
So from now on there should be no more hedgehogs having to be rescued from open excavations and the build work can now begin .That reminds me, I must check on the planning permission with the Maries office - it has gone really quite!!