Sunday, 6 November 2011

Roof complete.



Our roof is now complete, fully tiled and complete with roof lights. We now have a light airy space in what was once the Grenier and really looks fantastic with the natural stone walls that for 100 years haven't seen the light of day.



We now have some really interesting dynamics going on in the building which has again changed our thoughts on how we progress with the renovation works. It would be a crime not to keep areas of the stonework. So we have decided to re-point the front  and rear walls and to insulate and plasterboard the  gable.



    
 The next stage of the works is to look at the condition of the first floor joists. These are a cause of concern with several of the timbers being in poor condition. The floor is "bouncy" and slopes by around 50mm from one end to the other. So over next few days the builder is going to take a look at things and advise us on things.

Over the next few weeks it is planned to lay the new concrete floor and form the new door and window openings. The new hardwood double glazed doors and windows have been delivered. So it should be all go but this is France so we are not holding our breath!

1 comment:

  1. The completion of your roof marks the start of having a beautiful home.
    Kudos to you guys for making a very nice house. The owners must be so happy.

    -Mariam Freame

    ReplyDelete